Four decades after the Chernobyl disaster, it is evident that Ukraine’s nuclear sector has undergone a lasting shift toward risk management; rather than expansion, the priorities have become safety, reliability, and system resilience. The ongoing war has further tested this model, exposing the critical dependence of stable electricity generation on the power grid, as well as the operational risks associated with attacks on infrastructure and threats to the physical security of facilities. Nuclear power now serves as a reliable source of electricity, helping to limit supply fluctuations under conditions of wartime destruction.
The Importance of the Nuclear Sector in Ukraine. Nuclear energy is a key baseload source in Ukraine. In the years preceding Russia’s full-scale invasion, electricity generated by nuclear power plants typically accounted for approximately 50–55% of total electricity production, which – combined with the relatively stable operation of the reactor units – made nuclear power the most important component of the country’s power system (whereas other technologies more often played balancing, peak-load, or reserve roles). Such a structure has systemic implications. On the one hand, it reduces the risk of electricity shortages during periods of fluctuations in thermal generation and helps to stabilise the balance when hydrological conditions are unfavourable, or renewable energy output is lower. On the other hand, the high concentration of power generation in just a few large units increases vulnerability to grid constraints and outages, raises the importance of reserve capacity, and necessitates the development of balancing resources and greater grid-side flexibility. Ukraine has four nuclear power plants and a fleet of 15 VVER reactors with a combined capacity of approximately 13–14 GW, which, at the national level, constitutes one of the pillars of energy security (“IEŚ Commentaries”, No. 1552) and reduces pressure to use and import fossil fuels for electricity generation, especially during periods of high demand. Maintaining the sector, therefore, requires parallel investment in both the reliability of the transmission network and in the system’s balancing capabilities. Without doubt, the nuclear sector in Ukraine creates a specific interdependence between generation technology and the grid. The greater the share of baseload generation, the more important transmission capacity becomes (that is, the ability to evacuate power from a limited number of nodes), as does the quality of frequency and voltage regulation. In practice, this means that the key parameter of supply security is not solely reactor availability but also the resilience of the grid to damage, the ability to operate under transmission constraints, and access to flexibility resources (reserves and storage).
Ukraine’s Nuclear Sector Over the Past 40 Years. While the Chernobyl disaster did not bring nuclear power in Ukraine to a halt (“IEŚ Commentaries”, No. 382), it fundamentally changed its logic from expansion to risk management and reliability. A moratorium on new investments was introduced between 1990 and 1993, and the process of decommissioning Chernobyl (i.e., the cessation of electricity generation) was completed in 2000. Over time, sectoral policy shifted toward safety upgrades and the lifetime extension of units originally designed for approximately 30 years of operation. At the same time, the importance of the largest facilities increased, and in particular, the Zaporizhzhia Nuclear Power Plant (6 reactors, approx. 6 GW of capacity), which before 2022 was not only a key component of the national power balance but also the largest nuclear power plant in Europe.
After 1991, the sector developed under conditions of global economic transformation and declining electricity demand, which limited the scope for new investments and shifted attention from expansion to maintaining the operability of existing capacity. The decisive institutional turning point was the suspension of new projects in the early 1990s, followed by the shutdown of the Chernobyl plant, all of which reordered safety priorities and changed the way technological risk was understood. In subsequent years, the state and the operator focused on enhancing safety and extending the operation of existing units. At the same time, organisational and market frameworks were strengthened (including the consolidation of management within Energoatom), which was intended to facilitate the planning of replacement investments and the standardisation of operating practices. A persistent constraint remained the dependence on external nuclear fuel cycle services and the need to diversify supplies, which – under conditions of geopolitical tension – acquired strategic significance comparable to technical issues.
It is worth emphasising that the “lifetime extension” of reactor units is not merely a technical decision about refurbishment, but a policy model. It makes it possible to maintain generating capacity at relatively lower cost than building new units, but it shifts the burden onto regulatory institutions, safety culture, and the stable financing of modernisation. Under conditions of limited capital and high uncertainty – initially transitional, later wartime – extending the operation of existing units became a way to reduce the risk of capacity shortages. At the same time, this process exposed weaknesses in the supply chain, such as limited access to parts, engineering services, fuel, and supporting infrastructure. Since the diversification of nuclear fuel supplies is not a new challenge (in Ukraine, this process has been underway for a number of years), what has become equally important today is maintaining service capabilities and operational capacity under wartime conditions. Amid continuous Russian attacks on infrastructure, it is the ability to safely maintain and restore reactor operations that determines the fleet’s real long-term availability, rather than merely its formal authorisation for operation.
The Importance of Nuclear Power Plants Under Wartime Conditions. After 2022, the role of nuclear energy became even more important as the war primarily struck thermal generation and grid infrastructure, thereby constraining the system’s balancing capabilities. As a result, security of supply depends not only on the availability of generating capacity, but also on the ability to evacuate that power and maintain functioning systems under conditions of damage and operational constraints. Consequently, the three nuclear power plants remaining under Ukrainian control (with a total of 9 reactors) have become the principal stabilisers of electricity supply, although their role is increasingly dependent on the condition of the grid and the availability of flexible resources capable of compensating for fluctuations resulting from both from the destruction of infrastructure and from the growing share of variable generation. A key risk factor is the loss of the Zaporizhzhia Nuclear Power Plant, the largest in the country, whose occupation by Russia deprived the system of a significant share of baseload capacity and reduced its security “buffer,” increasing vulnerability to outages and transmission constraints. From a system perspective, synchronisation with the European ENTSO-E system (16 March 2022) was also important, as it opened up the possibility of supporting balancing through cross-border exchanges as well as strengthening the framework for operational stability. In the context of the country’s economic reconstruction once the war ends, nuclear energy would perform a dual function: first, it would provide relatively low-cost and low-carbon baseload electricity and, second, it would create a durable foundation for the reconstruction of industry and critical services. At the same time, its strong baseload character means that the success of its reconstruction will depend on parallel investments in the grid, balancing capacity (flexible resources such as hydropower, gas-fired, or coal-fired plants), as well as demand-side flexibility and storage, so that stable generation can be used effectively despite the infrastructure constraints and security risks.
Conclusions
Michał Paszkowski
IEŚ Commentaries 1605 (110/2026)
Ukraine’s Nuclear Sector 40 Years After the Chernobyl Disaster